Wednesday, January 25, 2012

Connie Phan - 1/24/2012

Activities and contribution

1. Started issue log
2. Completed coding back office methods for Posting

What are the challenges encountered

1. I run into a lot of issue with the IDE and getting glassfish to work on my local computer. Overall, my lack of

experience in Java and Eclipse is not allowing me to make as much progress as I woulk like

Plan for the next 7 days

1. Wire book posting UI to correct services
2. Implement unit test code for posting services
3. Start on book verify UI
4. Work on unit test and code review matrix

Wednesday, January 18, 2012

SE591 - Entry 1

Connie Phan - 1/16/2012

Activities and contribution

1. Completed detailed project plan and task assignments for phase 2
2. Started coding back office methods for Posting

What are the challenges encountered

1. Trying to get back into the code and the overall project momentum

Plan for the next 7 days

1. Complete back office and unit tests for Edit Posting screen
2. Start development for book verification